This whitepaper is for teams that need capacity math before they need a sales call. It gives three things: what physically ships, two fully-specified example rows built on today’s standard GPU servers, and a three-line estimate you can run yourself from a GPU count. Every assumption carries a label — [fact] for vendor-public specs, [canon] for numbers we hold ourselves to across this site, [est.] for estimates you should pressure-test. Nothing here is a quote; the quote comes after a site review.
Scope warning, up front: every dollar figure below is infrastructure capex only — the box, power, cooling, monitoring, delivery. GPU servers themselves are NOT included and their prices move monthly.
1. What ships
The FDC-P40 is a 40-ft high-cube container with the whole chain factory-installed: LV incomer, distribution, rack rows, cooling, monitoring. Two cooling tiers:
The line is two products, not three — air and liquid. (Hybrid dual-source plants exist in the industry; our three-chain analysis covers them as analysis, and we don’t sell one.)
| Product | Rack positions | IT capacity | Rack density | Design PUE | Cooling |
|---|---|---|---|---|---|
| FDC-P40-AC (air) | 18 IT + 2 network (single row, external cooling plant) — a 27-position back-to-back wind-wall flagship (500–750 kW) is ◐ vendor-claim, opens after third-party verification | 350 / 450 / 540 kW | 8–30 kW/rack | 1.40–1.50 (DX) / 1.15–1.45 (FC variant, climate) [est.] | Smart DX N+1 or fluorine-pump free cooling, rooftop/skid-mounted; no water either way |
| FDC-P40-LC (liquid) | 10–14 + CDU bay | 850 / 1,050 / 1,250 kW | 50–132 kW/rack | 1.15–1.20 [canon] | Cold plates + fluorine-to-water CDU + dry coolers; WUE ≈ 0 |
The rack count is where the two products genuinely differ: the air box has a fixed 18-IT single-row floor plan (cooling plant external) and the chip moves the tier; the liquid box trades rack positions for a CDU bay and manifold gallery (18 → 10–14) and gains 2–2.5× per-rack load — so per-container GPU count can go up even with fewer racks.
Delivery is the product: manufacturing (60–90 days) runs parallel to permitting, signature to first power bill in 6–9 months [canon] — against a five-year median grid-queue for a new build [S4].
2. Container AC — the two chip configurations [est., derived from public specs]
The air box has a fixed floor plan — 25 IT rack positions — so the chip changes the tier, not the rack count. Two factory configurations, both dry end to end:
| AC + H200 | AC + B300 | |
|---|---|---|
| Server | HGX H200 8-GPU (6U–8U chassis), ~10.5 kW [est.] | HGX B300 air node (~10U), ~13 kW [est.] — 1,100–1,400 W class ships air-cooled from four OEMs (memo) |
| Servers/rack | 2 | 2 |
| Rack load | 21 kW | 26 kW |
| Cooling plant | 6 × 80 kW DX or 4 × 120 kW fluorine-pump indoor units + external dry coolers — ~480 kW installed, N+1 → ~400 kW usable, consuming 4–6 rack positions | same |
| IT racks available | 18 of 25 | 15 of 25 |
| Container IT | ~380 kW | ~390 kW |
| Tier filled | AC-500 (electrical option; thermal fill tops ~400) | AC-750 (same thermal reality) |
| GPUs/container | 288 | 240 |
| PUE | 1.40–1.50 (DX) / 1.15–1.25 (FC, cool climate) [est.] | same |
Honesty note — the 500 kW question: recent market data is right that air-cooled containers rarely deliver 500 kW of AI fill. The 25-rack floor plan times 21 kW is not the constraint; the in-box cooling plant is. A 40-ft air box realistically delivers ~380–400 kW of dense GPU load. Everything below uses that honest number.
Fits the AC tier (8–30 kW/rack band). Choose AC-FC where the site’s free-cooling hours exceed ~50%; below that, plain AC or move to liquid — the kill conditions are in the working paper.
3. Container LC — the two chip configurations [est., derived from public specs]
Two factory configurations. This is where the rack count drops: the CDU bay and manifold gallery take the space the air box gives to racks — 18 positions become 10–14 — while per-rack load rises 2–2.5×. Each build ships with a 1+1 whole-unit CDU pair sized so one survivor carries the full IT load [canon, spec book §3.2].
| LC + H200 | LC + H200 (6U variant) | LC + B300 | |
|---|---|---|---|
| Server | H200 cold-plate, 8U chassis, ~10.5 kW [est.] | H200 cold-plate, 6U chassis, ~10.5 kW [est.] | B300 cold-plate (~10U), ~13.5 kW [est.] |
| GPU TDP | 700 W [fact] | 700 W [fact] | 1,400 W [fact] |
| Servers/rack | 5 | 6 | 4 |
| Rack load | 52.5 kW | 63 kW | 55 kW |
| Container | 12 IT racks (+ CDU bay) = 630 kW | 12 IT racks = 756 kW | 14 IT racks = 770 kW |
| Tier filled | LC-850 (74%) | LC-850 (89%) | LC-850 (91%) |
| GPUs/container | 480 | 576 | 448 |
| Cooling plant | 2 × 400 kW dual-pump CDU + external dry coolers (one bay; rack positions stay IT) | same | same |
Servers-per-rack is a chassis-height fact: 42U holds 5 × 8U nodes or 6 × 6U — the 576-GPU box commits you to a 6U chassis at server selection.
Scale reference: NVIDIA’s GB300 NVL72 runs the same silicon at ~135–140 kW/rack [fact] — 9–10 such racks fill an LC-1,250, a configuration variant priced separately. Water-to-water CDU variant available for retrofit sites with an existing chilled-water plant.
4. The three-line estimate
1. IT load = your GPU count ÷ 8 GPUs/server × per-server kW
2. Facility power = IT load × PUE (air 1.40–1.50, FC 1.15–1.45, liquid 1.10–1.20)
3. Infra capex = IT load (MW) × $3.6–4.9M/MW·IT [canon, import duties included]
(before-duties band: $2.8–4.0M/MW·IT)
Annual energy, if you want line four: IT × PUE × 8,760 h — at $0.07/kWh that is ~$0.61 M per MW of facility power per year [est., utility-rate dependent] (so a 2.0 MVA draw ≈ $1.2 M/yr, as in the worked check below).
5. Estimate worksheets
AC + H200 (2 servers/rack, 21 kW/rack — air box ~380-400 kW class)
| Your GPUs | Servers | Cabinets | IT load | Pod mapping | Infra capex [est.] | Utility feed [est.] |
|---|---|---|---|---|---|---|
| 64 | 8 | 4 | 84 kW | 1 × AC box, half-filled | $0.30–0.41 M | ~0.12 MVA |
| 288 | 36 | 18 | 378 kW | 1 × AC box (thermal fill limit) | $1.4–1.9 M | ~0.55 MVA |
| 576 | 72 | 36 | 756 kW | 2 × AC boxes | $2.7–3.7 M | ~1.1 MVA |
| 1,152 | 144 | 72 | 1,512 kW | 4 × AC boxes | $5.4–7.4 M | ~2.2 MVA |
AC + B300 (2 servers/rack, 26 kW/rack — air box ~390 kW class)
| Your GPUs | Servers | Racks | IT load | Container mapping | Infra capex [est.] | Utility feed [est.] |
|---|---|---|---|---|---|---|
| 240 | 30 | 15 | 390 kW | 1 × AC box (thermal fill limit) | $1.4–1.9 M | ~0.57 MVA |
| 480 | 60 | 30 | 780 kW | 2 × AC boxes | $2.8–3.8 M | ~1.13 MVA |
| 960 | 120 | 60 | 1,560 kW | 4 × AC boxes | $5.6–7.6 M | ~2.26 MVA |
LC + H200 (5 servers/rack 8U / 6 servers/rack 6U, 12 IT racks/container)
| Your GPUs | Servers | Racks | IT load | Container mapping | Infra capex [est.] | Utility feed [est.] |
|---|---|---|---|---|---|---|
| 480 | 60 | 12 | 630 kW | 1 × LC box (8U, 74%) | $2.3–3.1 M | ~0.73 MVA |
| 576 | 72 | 12 | 756 kW | 1 × LC box (6U variant, 89%) | $2.7–3.7 M | ~0.87 MVA |
| 1,152 | 144 | 24 | 1,512 kW | 2 × LC box | $5.4–7.4 M | ~1.74 MVA |
| 2,304 | 288 | 48 | 3,024 kW | 4 × LC box | $10.9–14.8 M | ~3.48 MVA |
LC + B300 (4 servers/rack, 55 kW/rack, 14 IT racks/container)
| Your GPUs | Servers | Cabinets | IT load | Pod mapping | Infra capex [est.] | Utility feed [est.] |
|---|---|---|---|---|---|---|
| 256 | 32 | 8 | 432 kW | 1 × LC-850 (half-filled, upgrade path) | $1.6–2.1 M | ~0.50 MVA |
| 1,024 | 128 | 32 | 1,728 kW | LC-850 + LC-1,050 | $6.2–8.5 M | ~2.0 MVA |
| 2,048 | 256 | 64 | 3,456 kW | 5 × LC box (4.5 boxes; 5th half-filled) | $12.4–16.9 M | ~4.0 MVA |
Container-per-GPU summary
| Container | + H200 | + B300 |
|---|---|---|
| AC (~400 kW thermal class) | 288 GPUs · ~380 kW | 240 GPUs · ~390 kW |
| LC (CDU bay, 12–14 racks) | 480 GPUs (8U) / 576 (6U) · 630–756 kW | 448 GPUs · 770 kW |
The density sleeper: cold-plating the 700 W H200 into a 6U chassis (6/rack) puts more GPUs in one 40-ft box than any other config. The per-GPU performance winner, at 2× the TDP, is LC + B300. And the air box’s honest ceiling — ~380–400 kW, set by its in-box cooling plant, not its floor plan — is exactly why the market rarely sees a 500 kW air container.
Worked check on the 1,024-GPU B300 line: 1,024 ÷ 8 = 128 servers × 13.5 kW = 1,728 kW IT → × $3.6–4.9 M/MW = $6.2–8.5 M. Facility power 1,728 × 1.15 ≈ 2.0 MVA feed. Annual energy ≈ 17.4 GWh → ~$1.2 M/yr at $0.07/kWh [est.].
6. What is NOT in these numbers
- GPU servers — the largest line item in any AI build, priced separately and moving monthly.
- Land, pad, and medium-voltage upgrade — the pod takes one LV feeder; if your site needs an MV to LV transformation stage, that’s a separate civil package.
- Network fabric and storage — inside the cabinets’ customers’ equipment, not ours.
- Opex beyond energy — staffing, security, network transit.
- The import-duty line — included in the $3.6–4.9 M band; if your supply chain changes, use the before-duties band and re-add duty at the prevailing rate.
7. Confidence and sources
[fact]NVIDIA public specs: H200 SXM 700 W; B300 (Blackwell Ultra) 1,400 W; GB300 NVL72 rack ~135–140 kW, fully liquid-cooled.[canon]Site-held numbers: pod tiers and density bands (turnkey pod spec); capex band incl. tariff (pod page pricing ladder); 6–9 month delivery (delivery playbook).[est.]Per-server input power, fluorine-pump PUE by climate, all worksheet multiplications, energy cost at an assumed $0.07/kWh. Pressure-test these first.- Working papers with per-layer sizing and kill conditions:
docs/pod-research/02in the project repo; the three-chain anatomy shows the topology the numbers assume.
8. Next step
Run your GPU count through §4, write down the two or three assumptions you’d dispute, and bring them to us — the estimate call is free and the disputes are the point. Every quote ships with the same model we run our own capital through, kill conditions included.