How to spec and price a container data center (2026)

2026-10-31 · Product brief · FlareDC

Markdown source: /downloads/$container-dc-estimator.md

Download this document: container-dc-2026.md (raw Markdown, same content as this page).

This whitepaper is for teams that need capacity math before they need a sales call. It gives three things: what physically ships, two fully-specified example rows built on today’s standard GPU servers, and a three-line estimate you can run yourself from a GPU count. Every assumption carries a label — [fact] for vendor-public specs, [canon] for numbers we hold ourselves to across this site, [est.] for estimates you should pressure-test. Nothing here is a quote; the quote comes after a site review.

Scope warning, up front: every dollar figure below is infrastructure capex only — the box, power, cooling, monitoring, delivery. GPU servers themselves are NOT included and their prices move monthly.

1. What ships

The FDC-P40 is a 40-ft high-cube container with the whole chain factory-installed: LV incomer, distribution, rack rows, cooling, monitoring. Two cooling tiers:

The line is two products, not three — air and liquid. (Hybrid dual-source plants exist in the industry; our three-chain analysis covers them as analysis, and we don’t sell one.)

ProductRack positionsIT capacityRack densityDesign PUECooling
FDC-P40-AC (air)18 IT + 2 network (single row, external cooling plant) — a 27-position back-to-back wind-wall flagship (500–750 kW) is ◐ vendor-claim, opens after third-party verification350 / 450 / 540 kW8–30 kW/rack1.40–1.50 (DX) / 1.15–1.45 (FC variant, climate) [est.]Smart DX N+1 or fluorine-pump free cooling, rooftop/skid-mounted; no water either way
FDC-P40-LC (liquid)10–14 + CDU bay850 / 1,050 / 1,250 kW50–132 kW/rack1.15–1.20 [canon]Cold plates + fluorine-to-water CDU + dry coolers; WUE ≈ 0

The rack count is where the two products genuinely differ: the air box has a fixed 18-IT single-row floor plan (cooling plant external) and the chip moves the tier; the liquid box trades rack positions for a CDU bay and manifold gallery (18 → 10–14) and gains 2–2.5× per-rack load — so per-container GPU count can go up even with fewer racks.

Delivery is the product: manufacturing (60–90 days) runs parallel to permitting, signature to first power bill in 6–9 months [canon] — against a five-year median grid-queue for a new build [S4].

2. Container AC — the two chip configurations [est., derived from public specs]

The air box has a fixed floor plan — 25 IT rack positions — so the chip changes the tier, not the rack count. Two factory configurations, both dry end to end:

AC + H200AC + B300
ServerHGX H200 8-GPU (6U–8U chassis), ~10.5 kW [est.]HGX B300 air node (~10U), ~13 kW [est.] — 1,100–1,400 W class ships air-cooled from four OEMs (memo)
Servers/rack22
Rack load21 kW26 kW
Cooling plant6 × 80 kW DX or 4 × 120 kW fluorine-pump indoor units + external dry coolers — ~480 kW installed, N+1 → ~400 kW usable, consuming 4–6 rack positionssame
IT racks available18 of 2515 of 25
Container IT~380 kW~390 kW
Tier filledAC-500 (electrical option; thermal fill tops ~400)AC-750 (same thermal reality)
GPUs/container288240
PUE1.40–1.50 (DX) / 1.15–1.25 (FC, cool climate) [est.]same

Honesty note — the 500 kW question: recent market data is right that air-cooled containers rarely deliver 500 kW of AI fill. The 25-rack floor plan times 21 kW is not the constraint; the in-box cooling plant is. A 40-ft air box realistically delivers ~380–400 kW of dense GPU load. Everything below uses that honest number.

Fits the AC tier (8–30 kW/rack band). Choose AC-FC where the site’s free-cooling hours exceed ~50%; below that, plain AC or move to liquid — the kill conditions are in the working paper.

3. Container LC — the two chip configurations [est., derived from public specs]

Two factory configurations. This is where the rack count drops: the CDU bay and manifold gallery take the space the air box gives to racks — 18 positions become 10–14 — while per-rack load rises 2–2.5×. Each build ships with a 1+1 whole-unit CDU pair sized so one survivor carries the full IT load [canon, spec book §3.2].

LC + H200LC + H200 (6U variant)LC + B300
ServerH200 cold-plate, 8U chassis, ~10.5 kW [est.]H200 cold-plate, 6U chassis, ~10.5 kW [est.]B300 cold-plate (~10U), ~13.5 kW [est.]
GPU TDP700 W [fact]700 W [fact]1,400 W [fact]
Servers/rack564
Rack load52.5 kW63 kW55 kW
Container12 IT racks (+ CDU bay) = 630 kW12 IT racks = 756 kW14 IT racks = 770 kW
Tier filledLC-850 (74%)LC-850 (89%)LC-850 (91%)
GPUs/container480576448
Cooling plant2 × 400 kW dual-pump CDU + external dry coolers (one bay; rack positions stay IT)samesame

Servers-per-rack is a chassis-height fact: 42U holds 5 × 8U nodes or 6 × 6U — the 576-GPU box commits you to a 6U chassis at server selection.

Scale reference: NVIDIA’s GB300 NVL72 runs the same silicon at ~135–140 kW/rack [fact] — 9–10 such racks fill an LC-1,250, a configuration variant priced separately. Water-to-water CDU variant available for retrofit sites with an existing chilled-water plant.

4. The three-line estimate

1. IT load        = your GPU count ÷ 8 GPUs/server × per-server kW
2. Facility power = IT load × PUE          (air 1.40–1.50, FC 1.15–1.45, liquid 1.10–1.20)
3. Infra capex    = IT load (MW) × $3.6–4.9M/MW·IT   [canon, import duties included]
                    (before-duties band: $2.8–4.0M/MW·IT)

Annual energy, if you want line four: IT × PUE × 8,760 h — at $0.07/kWh that is ~$0.61 M per MW of facility power per year [est., utility-rate dependent] (so a 2.0 MVA draw ≈ $1.2 M/yr, as in the worked check below).

5. Estimate worksheets

AC + H200 (2 servers/rack, 21 kW/rack — air box ~380-400 kW class)

Your GPUsServersCabinetsIT loadPod mappingInfra capex [est.]Utility feed [est.]
648484 kW1 × AC box, half-filled$0.30–0.41 M~0.12 MVA
2883618378 kW1 × AC box (thermal fill limit)$1.4–1.9 M~0.55 MVA
5767236756 kW2 × AC boxes$2.7–3.7 M~1.1 MVA
1,152144721,512 kW4 × AC boxes$5.4–7.4 M~2.2 MVA

AC + B300 (2 servers/rack, 26 kW/rack — air box ~390 kW class)

Your GPUsServersRacksIT loadContainer mappingInfra capex [est.]Utility feed [est.]
2403015390 kW1 × AC box (thermal fill limit)$1.4–1.9 M~0.57 MVA
4806030780 kW2 × AC boxes$2.8–3.8 M~1.13 MVA
960120601,560 kW4 × AC boxes$5.6–7.6 M~2.26 MVA

LC + H200 (5 servers/rack 8U / 6 servers/rack 6U, 12 IT racks/container)

Your GPUsServersRacksIT loadContainer mappingInfra capex [est.]Utility feed [est.]
4806012630 kW1 × LC box (8U, 74%)$2.3–3.1 M~0.73 MVA
5767212756 kW1 × LC box (6U variant, 89%)$2.7–3.7 M~0.87 MVA
1,152144241,512 kW2 × LC box$5.4–7.4 M~1.74 MVA
2,304288483,024 kW4 × LC box$10.9–14.8 M~3.48 MVA

LC + B300 (4 servers/rack, 55 kW/rack, 14 IT racks/container)

Your GPUsServersCabinetsIT loadPod mappingInfra capex [est.]Utility feed [est.]
256328432 kW1 × LC-850 (half-filled, upgrade path)$1.6–2.1 M~0.50 MVA
1,024128321,728 kWLC-850 + LC-1,050$6.2–8.5 M~2.0 MVA
2,048256643,456 kW5 × LC box (4.5 boxes; 5th half-filled)$12.4–16.9 M~4.0 MVA

Container-per-GPU summary

Container+ H200+ B300
AC (~400 kW thermal class)288 GPUs · ~380 kW240 GPUs · ~390 kW
LC (CDU bay, 12–14 racks)480 GPUs (8U) / 576 (6U) · 630–756 kW448 GPUs · 770 kW

The density sleeper: cold-plating the 700 W H200 into a 6U chassis (6/rack) puts more GPUs in one 40-ft box than any other config. The per-GPU performance winner, at 2× the TDP, is LC + B300. And the air box’s honest ceiling — ~380–400 kW, set by its in-box cooling plant, not its floor plan — is exactly why the market rarely sees a 500 kW air container.

Worked check on the 1,024-GPU B300 line: 1,024 ÷ 8 = 128 servers × 13.5 kW = 1,728 kW IT → × $3.6–4.9 M/MW = $6.2–8.5 M. Facility power 1,728 × 1.15 ≈ 2.0 MVA feed. Annual energy ≈ 17.4 GWh → ~$1.2 M/yr at $0.07/kWh [est.].

6. What is NOT in these numbers

  1. GPU servers — the largest line item in any AI build, priced separately and moving monthly.
  2. Land, pad, and medium-voltage upgrade — the pod takes one LV feeder; if your site needs an MV to LV transformation stage, that’s a separate civil package.
  3. Network fabric and storage — inside the cabinets’ customers’ equipment, not ours.
  4. Opex beyond energy — staffing, security, network transit.
  5. The import-duty line — included in the $3.6–4.9 M band; if your supply chain changes, use the before-duties band and re-add duty at the prevailing rate.

7. Confidence and sources

  • [fact] NVIDIA public specs: H200 SXM 700 W; B300 (Blackwell Ultra) 1,400 W; GB300 NVL72 rack ~135–140 kW, fully liquid-cooled.
  • [canon] Site-held numbers: pod tiers and density bands (turnkey pod spec); capex band incl. tariff (pod page pricing ladder); 6–9 month delivery (delivery playbook).
  • [est.] Per-server input power, fluorine-pump PUE by climate, all worksheet multiplications, energy cost at an assumed $0.07/kWh. Pressure-test these first.
  • Working papers with per-layer sizing and kill conditions: docs/pod-research/02 in the project repo; the three-chain anatomy shows the topology the numbers assume.

8. Next step

Run your GPU count through §4, write down the two or three assumptions you’d dispute, and bring them to us — the estimate call is free and the disputes are the point. Every quote ships with the same model we run our own capital through, kill conditions included.