From Signature to Power Bill: The Pod Delivery Playbook

2026-10-30 · Technical reference · FlareDC

Markdown source: /downloads/$pod-delivery-playbook.md

The pod is a machine for turning an energized feeder into billing racks within a quarter. This is the process document: the stage-by-stage path from signature to first power bill, the acceptance tests the equipment passes twice — once in the factory, once on your pad — and the site works you schedule in parallel. We publish it because we quote from it. If a step surprises you at week 14, it shouldn’t have.

The schedule

StageDurationNote
Design freeze2–4 wksCooling version, tier, rack & PDU schedules, UPS yes/no — both production lines start here
Permits & power application (parallel)3–6 moThe critical path; policy-pause risks are screened at siting, before signature
Factory build + FAT60–90 daysAll mature components, no long-lead parts
Ocean / road freight3–5 wks40-ft high-cube books as standard freight
On site: land, connect, SAT1–2 wks air / 2–4 wks liquidLiquid includes external dry-cooler rigging
Rack + energize3–7 daysPDUs pre-wired to your outlet schedule
Signature → power bill~6–9 monthsWhen permitting and manufacturing run in parallel

The one scheduling rule: the factory never waits on the permit. A 60–90-day factory cannot make a 6-month permit arrive faster — it can only be wasted waiting for one. Design freeze triggers both lines at once, and the pad cures inside the manufacturing window (28-day standard cure, 14-day early-strength mix as an option [est.]).

FAT: the tests it passes before it sees a truck

Factory acceptance is a judged event, not a checklist waved through. Every tier runs the full program (criteria are industry practice, finalized in the technical agreement):

#TestPass criterion
1Insulation resistance / withstand on busway and distribution circuitsIEC 61439 / UL 891 clauses
2ACB protection settings and cascade (long/short/instant, ground fault)Settings sheet, item by item
3Dummy load: 100% for 24 h, then 110% for 1 hNo trips, no smells, temperature rise in spec
4PDU branch balance and every outlet100% match to your schedule
5Cooling 48 h trial + N+1 changeoverNo interruption on pump/compressor switchover
6(Liquid) Water side at 1.5× working pressure, quality report, leak interlockNo seepage; interlock trips <10 s
7Fire chain: VESDA staged alarms → clean-agent release → shutdown interlockLive test, gas replaced with nitrogen
8SCADA/DCIM point table (telemetry, status, control)100% of points verified
9Noise and vibration at full load<75 dB air / <72 dB liquid [est.]
10Post-transport re-inspection on arrivalNo loose assemblies before SAT begins

SAT: the tests it passes on your pad

After the crane leaves: level and anchorage check → grounding resistance ≤4 Ω (or local code) → energization sequence rehearsal (incomer → busway → feeders, step by step) → 8 h dummy load including summer and night cooling modes → fire interlock retest → IT interface check against your rack plan → document pack handover → acceptance certificate signed.

The warranty clock starts at SAT signature — not when the truck leaves the factory, and not when the container lands.

The pad: what you pour, and when

ItemSpec
Size≥13.5 × 3.5 m (the 12.19 × 2.44 m box plus 0.6–0.7 m service aisle all round); liquid adds a dry-cooler foundation ~4 × 2 m beside the pod or a roof-mounted frame
LoadingDesigned for full load: empty pod 11–17 t + IT equipment 8–12 t + coolant/batteries + dynamic load → ≥15 kPa distributed, ≥10 t per corner casting; design total 25–30 t
Drainage1–2% slope away from the box; liquid pods tie the underfloor catch tray to site drainage
GroundingGrid ≤4 Ω, bonded to the incoming PE at a single point
Embedded ducts2 × 150 mm LV cable, 2 × 100 mm dual-route fiber (plus dry-cooler pipe sleeve if liquid)
WindASCE 7-22 by county — coastal counties at 160 mph+ basic wind speed need a dedicated anchorage calculation [est.]
SeismicIBC / ASCE 7 by site SDC class

Pour the pad inside the manufacturing window. A pad that cures while the pod builds costs zero days; one that starts after the pod lands costs exactly the difference.

What ships with the pod

  • Warranty: 12 months on structure, power and monitoring; 3–5 years on compressors and CDU pumps per vendor terms; 10 years anti-corrosion on the enclosure. Clock starts at SAT.
  • Documents: SLD, layout, cooling piping and foundation drawings; full FAT/SAT reports including load curves and water quality; SCADA point list and protocol map (IEC 61850 / Modbus); O&M manuals with the >45 °C derating curves and the summer dry-cooler strategy; UL/CE certificates per destination.
  • Spares: ACB contacts and trip unit, 2 × EC fans, 1 × CDU pump, filters, a spare leak-detection rope segment.
  • Support: SLA template with 7×24 remote monitoring — deployed pods route to [email protected].

Where engagements slip, and how this playbook keeps them from slipping

  1. Permits. The factory cannot help you here; parallel is the only path. Permit-moratorium-type policy risk is screened at siting — before signature, not after.
  2. Feeder mis-sizing. Sized at nameplate IT, the incomer trips the first full-load summer afternoon. The ×PUE rule lives in the contract’s technical annex — see the electrical first account — never in a verbal note.
  3. Medium-voltage-only sites. The transformer variant (pad-mount or bay container) is priced and scheduled at design freeze, not discovered at delivery.
  4. Derating by stealth. Above 45 °C ambient the cooling plant derates; the SLA is written on derated summer capacity, not nameplate [est.]. If a vendor won’t write that down, ask why.

The one-line version

Permits and concrete run in parallel with steel and copper; the equipment is tested twice — once in the factory, once on your pad — and the warranty starts when it passes on your side, not when it leaves ours. The pod itself is spec’d here; the engagements this playbook serves are here.