From Signature to Power Bill: The Pod Delivery Playbook
The pod is a machine for turning an energized feeder into billing racks within a quarter. This is the process document: the stage-by-stage path from signature to first power bill, the acceptance tests the equipment passes twice — once in the factory, once on your pad — and the site works you schedule in parallel. We publish it because we quote from it. If a step surprises you at week 14, it shouldn’t have.
The schedule
| Stage | Duration | Note |
|---|---|---|
| Design freeze | 2–4 wks | Cooling version, tier, rack & PDU schedules, UPS yes/no — both production lines start here |
| Permits & power application (parallel) | 3–6 mo | The critical path; policy-pause risks are screened at siting, before signature |
| Factory build + FAT | 60–90 days | All mature components, no long-lead parts |
| Ocean / road freight | 3–5 wks | 40-ft high-cube books as standard freight |
| On site: land, connect, SAT | 1–2 wks air / 2–4 wks liquid | Liquid includes external dry-cooler rigging |
| Rack + energize | 3–7 days | PDUs pre-wired to your outlet schedule |
| Signature → power bill | ~6–9 months | When permitting and manufacturing run in parallel |
The one scheduling rule: the factory never waits on the permit. A 60–90-day factory cannot make a 6-month permit arrive faster — it can only be wasted waiting for one. Design freeze triggers both lines at once, and the pad cures inside the manufacturing window (28-day standard cure, 14-day early-strength mix as an option [est.]).
FAT: the tests it passes before it sees a truck
Factory acceptance is a judged event, not a checklist waved through. Every tier runs the full program (criteria are industry practice, finalized in the technical agreement):
| # | Test | Pass criterion |
|---|---|---|
| 1 | Insulation resistance / withstand on busway and distribution circuits | IEC 61439 / UL 891 clauses |
| 2 | ACB protection settings and cascade (long/short/instant, ground fault) | Settings sheet, item by item |
| 3 | Dummy load: 100% for 24 h, then 110% for 1 h | No trips, no smells, temperature rise in spec |
| 4 | PDU branch balance and every outlet | 100% match to your schedule |
| 5 | Cooling 48 h trial + N+1 changeover | No interruption on pump/compressor switchover |
| 6 | (Liquid) Water side at 1.5× working pressure, quality report, leak interlock | No seepage; interlock trips <10 s |
| 7 | Fire chain: VESDA staged alarms → clean-agent release → shutdown interlock | Live test, gas replaced with nitrogen |
| 8 | SCADA/DCIM point table (telemetry, status, control) | 100% of points verified |
| 9 | Noise and vibration at full load | <75 dB air / <72 dB liquid [est.] |
| 10 | Post-transport re-inspection on arrival | No loose assemblies before SAT begins |
SAT: the tests it passes on your pad
After the crane leaves: level and anchorage check → grounding resistance ≤4 Ω (or local code) → energization sequence rehearsal (incomer → busway → feeders, step by step) → 8 h dummy load including summer and night cooling modes → fire interlock retest → IT interface check against your rack plan → document pack handover → acceptance certificate signed.
The warranty clock starts at SAT signature — not when the truck leaves the factory, and not when the container lands.
The pad: what you pour, and when
| Item | Spec |
|---|---|
| Size | ≥13.5 × 3.5 m (the 12.19 × 2.44 m box plus 0.6–0.7 m service aisle all round); liquid adds a dry-cooler foundation ~4 × 2 m beside the pod or a roof-mounted frame |
| Loading | Designed for full load: empty pod 11–17 t + IT equipment 8–12 t + coolant/batteries + dynamic load → ≥15 kPa distributed, ≥10 t per corner casting; design total 25–30 t |
| Drainage | 1–2% slope away from the box; liquid pods tie the underfloor catch tray to site drainage |
| Grounding | Grid ≤4 Ω, bonded to the incoming PE at a single point |
| Embedded ducts | 2 × 150 mm LV cable, 2 × 100 mm dual-route fiber (plus dry-cooler pipe sleeve if liquid) |
| Wind | ASCE 7-22 by county — coastal counties at 160 mph+ basic wind speed need a dedicated anchorage calculation [est.] |
| Seismic | IBC / ASCE 7 by site SDC class |
Pour the pad inside the manufacturing window. A pad that cures while the pod builds costs zero days; one that starts after the pod lands costs exactly the difference.
What ships with the pod
- Warranty: 12 months on structure, power and monitoring; 3–5 years on compressors and CDU pumps per vendor terms; 10 years anti-corrosion on the enclosure. Clock starts at SAT.
- Documents: SLD, layout, cooling piping and foundation drawings; full FAT/SAT reports including load curves and water quality; SCADA point list and protocol map (IEC 61850 / Modbus); O&M manuals with the >45 °C derating curves and the summer dry-cooler strategy; UL/CE certificates per destination.
- Spares: ACB contacts and trip unit, 2 × EC fans, 1 × CDU pump, filters, a spare leak-detection rope segment.
- Support: SLA template with 7×24 remote monitoring — deployed pods route to [email protected].
Where engagements slip, and how this playbook keeps them from slipping
- Permits. The factory cannot help you here; parallel is the only path. Permit-moratorium-type policy risk is screened at siting — before signature, not after.
- Feeder mis-sizing. Sized at nameplate IT, the incomer trips the first full-load summer afternoon. The ×PUE rule lives in the contract’s technical annex — see the electrical first account — never in a verbal note.
- Medium-voltage-only sites. The transformer variant (pad-mount or bay container) is priced and scheduled at design freeze, not discovered at delivery.
- Derating by stealth. Above 45 °C ambient the cooling plant derates; the SLA is written on derated summer capacity, not nameplate [est.]. If a vendor won’t write that down, ask why.
The one-line version
Permits and concrete run in parallel with steel and copper; the equipment is tested twice — once in the factory, once on your pad — and the warranty starts when it passes on your side, not when it leaves ours. The pod itself is spec’d here; the engagements this playbook serves are here.