Scenario Engineering case · air first

H200 fleet,
air first

Mature hardware · 0.4 MW class · CDU-ready by design

Single-row air-cooled container with external rooftop cooling plant, cold air in from the left and hot air out to the right

The case: your fleet is H200 (or air-node B300), your site has 480 V service and no water to spare, and you value bankable over bleeding-edge. Air is the fastest, simplest path — every component is mature, nothing waits on a roadmap. The honest ceiling is the box's heat-rejection budget, not its floor plan: ~380–400 kW for dense GPU fills, which is why "0.4 MW class" is the whole air story and the market norm is 170–300 kW.

288
GPUs per container (2 × 8-GPU H200 × 18 racks)
~380 kW
Container IT — the optimistic top of the 170–300 kW shipping norm
18 IT
Single-row floor plan — cooling plant external, no floor position pays for it
CDU-ready
CDU position, pipework and leak tray pre-installed: swap servers, not the container

What's inside · products

Tech behind · technology

The full brief · on the record

The configuration working paper for this scenario — 2 servers/rack at 21 kW, why the GPU count drops as racks run hotter, the FC-variant free-cooling arithmetic — is the modular air + H200 solution brief. The product spec lives on the FDC-P40-AC page; siting math is in the three Texas verdicts.

Kill conditions: free-cooling hours below ~50% → drop the FC variant, take plain DX. NVL72-class systems or sustained loads above 30 kW/rack → that's not this box — go liquid.

Size this scenario for your site Compare the liquid case