Power In, Servers In, Revenue Out: The Turnkey Pod, Spec'd
A turnkey data center pod is a 40-ft high-cube container with everything factory-installed: LV incomer, distribution busway, rack rows, cooling, monitoring. The customer’s moves are exactly three — pour a pad, land one low-voltage feeder, plug in fiber — then rack servers and close the breaker. Power bill the same month, rent the same quarter.
Why LV-direct-in is the product
The pod skips the entire “10 kV → dry transformer → LV switchgear” civil-works stage — the most expensive, slowest, permit-heaviest slice of a traditional build. Any industrial site with 380/400V (CN) or 480V (US) service feeds the pod directly. Every component is mature 2026 hardware; nothing in the BOM waits on a 2028 roadmap. (The 800 VDC / SST path is a separate track — the pod’s power bay is designed to swap to it later, box and cooling unchanged.)
Two cooling tiers, one power chain
| Version | IT capacity | Rack density | Design PUE |
|---|---|---|---|
| Air (smart DX, N+1) | 500 / 600 / 750 kW | 8–30 kW/rack | 1.40–1.50 |
| Liquid (cold-plate DLC) | 850 / 1050 / 1250 kW | 50–132 kW/rack | 1.15–1.20 |
The rule of thumb: server form factor picks the cooler. 2U/4U air-cooled nodes → air version. NVL72-class or cold-plate GPU nodes → liquid. Air-cooled pods ship with the CDU position, pipework, and leak-detection tray pre-installed, so a later liquid retrofit swaps servers, not the container.
The one multiplication that matters
Size the feeder at IT × PUE ÷ 0.99, never at nameplate IT. The 750 kW air tier draws ~1,088 kW of facility load at PUE 1.45 — about 1,320 A at 480V, 1,670 A at 380V — so the incomer is a 2,000 A frame. Feed it nameplate current and it trips the first summer afternoon at full load. This single ×PUE is the most common quoting disaster in pod sales.
Money and time
- Landed cost: air $2.8–4.0M/MW before import duties, $3.6–4.9M with duties included; liquid ×1.15. That’s 25–50% of the JLL 2026 new-build average ($11.3M/MW) — the spread is the margin pool.
- Schedule: 60–90 days in the factory, 1–2 weeks on site (air) or 2–4 (liquid). The critical path is permits — roughly 6 months, which is why permitting and power applications must run parallel to manufacturing. Signature to first power bill: ~6–9 months.
- Revenue: a 1.25 MW liquid pod at $195/kW/month grosses ~$2.93M/yr; on Duos-style contract pricing, ~$2.3M/yr. Yield-on-cost lands around 20–40% depending on tariff treatment.
Redundancy is honest: the default config is ≈ Tier I (single feed, no UPS, cooling N+1); dual-feed, UPS, and 2N cooling are options that buy Tier II–III. Confirm the customer’s tier expectation before quoting — the expectation gap is where colo deals go to die. And every pod ships through a factory acceptance test (100% load for 24 h, 110% for 1 h) before it ever sees a truck.
The one-line version
The pod’s value was never power conversion — LV goes straight in. It’s factory-prefab + turnkey + fast: a machine for turning an energized feeder into billing racks within one quarter. The full spec — both versions, the per-tier current table, the delivery schedule, the price ladder — lives on the FDC-P40 product page. See it opened up in the container cutaway, and the per-MW arithmetic in the cost reference.