# The Container Data Center, 2026: Example Specs and a Three-Line Estimate (H200 / B300)

2026-10-31 · FlareDC — flaredc.com

---

**Download this document:** [container-dc-2026.md](/downloads/container-dc-2026.md) (raw Markdown, same content as this page).

This whitepaper is for teams that need capacity math before they need a sales call. It gives three things: what physically ships, two fully-specified example rows built on today's standard GPU servers, and a three-line estimate you can run yourself from a GPU count. Every assumption carries a label — `[fact]` for vendor-public specs, `[canon]` for numbers we hold ourselves to across this site, `[est.]` for estimates you should pressure-test. Nothing here is a quote; the quote comes after a site review.

**Scope warning, up front:** every dollar figure below is **infrastructure capex only** — the box, power, cooling, monitoring, delivery. **GPU servers themselves are NOT included** and their prices move monthly.

## 1. What ships

The [FDC-P40](/products/pod/) is a 40-ft high-cube container with the whole chain factory-installed: LV incomer, distribution, rack rows, cooling, monitoring. Two cooling tiers:

The line is **two products, not three** — air and liquid. (Hybrid dual-source plants exist in the industry; our [three-chain analysis](/technology/modular/) covers them as analysis, and we don't sell one.)

| Product | Rack positions | IT capacity | Rack density | Design PUE | Cooling |
|---|---|---|---|---|---|
| **[FDC-P40-AC](/products/pod/air/)** (air) | **18 IT + 2 network (single row, external cooling plant)** — a 27-position back-to-back wind-wall flagship (500–750 kW) is ◐ vendor-claim, opens after third-party verification | 350 / 450 / 540 kW | 8–30 kW/rack | 1.40–1.50 (DX) / 1.15–1.45 (FC variant, climate) `[est.]` | Smart DX N+1 or fluorine-pump free cooling, rooftop/skid-mounted; no water either way |
| **[FDC-P40-LC](/products/pod/liquid/)** (liquid) | **10–14 + CDU bay** | 850 / 1,050 / 1,250 kW | 50–132 kW/rack | 1.15–1.20 `[canon]` | Cold plates + fluorine-to-water CDU + dry coolers; WUE ≈ 0 |

**The rack count is where the two products genuinely differ**: the air box has a fixed 18-IT single-row floor plan (cooling plant external) and the chip moves the tier; the liquid box trades rack positions for a CDU bay and manifold gallery (18 → 10–14) and gains 2–2.5× per-rack load — so per-container GPU count can go *up* even with fewer racks.

Delivery is the product: manufacturing (60–90 days) runs parallel to permitting, **signature to first power bill in 6–9 months** `[canon]` — against a five-year median grid-queue for a new build <sup><a href="/solutions/academic-anchors/" title="Sources — the receipts">[S4]</a></sup>.

## 2. Container AC — the two chip configurations `[est.`, derived from public specs]

The air box has a **fixed floor plan — 25 IT rack positions** — so the chip changes the tier, not the rack count. Two factory configurations, both dry end to end:

| | **AC + H200** | **AC + B300** |
|---|---|---|
| Server | HGX H200 8-GPU (6U–8U chassis), ~10.5 kW `[est.]` | HGX B300 **air node** (~10U), ~13 kW `[est.]` — 1,100–1,400 W class ships air-cooled from four OEMs ([memo](/solutions/air-cooled-b300/)) |
| Servers/rack | 2 | 2 |
| Rack load | 21 kW | 26 kW |
| Cooling plant | 6 × 80 kW DX or 4 × 120 kW fluorine-pump indoor units + external dry coolers — **~480 kW installed, N+1 → ~400 kW usable**, consuming 4–6 rack positions | same |
| IT racks available | 18 of 25 | 15 of 25 |
| Container IT | **~380 kW** | **~390 kW** |
| Tier filled | AC-500 (electrical option; thermal fill tops ~400) | AC-750 (same thermal reality) |
| **GPUs/container** | **288** | **240** |
| PUE | 1.40–1.50 (DX) / 1.15–1.25 (FC, cool climate) `[est.]` | same |

**Honesty note — the 500 kW question:** recent market data is right that air-cooled
containers rarely deliver 500 kW of AI fill. The 25-rack floor plan times 21 kW is not the
constraint; the **in-box cooling plant is**. A 40-ft air box realistically delivers
**~380–400 kW** of dense GPU load. Everything below uses that honest number.

Fits the **AC tier** (8–30 kW/rack band). Choose AC-FC where the site's free-cooling hours exceed ~50%; below that, plain AC or move to liquid — the kill conditions are in the working paper.

## 3. Container LC — the two chip configurations `[est.`, derived from public specs]

Two factory configurations. **This is where the rack count drops**: the CDU bay and manifold gallery take the space the air box gives to racks — 18 positions become 10–14 — while per-rack load rises 2–2.5×. Each build ships with a 1+1 whole-unit CDU pair sized so one survivor carries the full IT load `[canon, spec book §3.2]`.

| | **LC + H200** | **LC + H200 (6U variant)** | **LC + B300** |
|---|---|---|---|
| Server | H200 cold-plate, 8U chassis, ~10.5 kW `[est.]` | H200 cold-plate, **6U chassis**, ~10.5 kW `[est.]` | B300 cold-plate (~10U), ~13.5 kW `[est.]` |
| GPU TDP | 700 W `[fact]` | 700 W `[fact]` | 1,400 W `[fact]` |
| Servers/rack | 5 | **6** | 4 |
| Rack load | 52.5 kW | 63 kW | 55 kW |
| Container | 12 IT racks (+ CDU bay) = **630 kW** | 12 IT racks = **756 kW** | 14 IT racks = **770 kW** |
| Tier filled | LC-850 (74%) | LC-850 (89%) | LC-850 (91%) |
| **GPUs/container** | **480** | **576** | **448** |
| Cooling plant | 2 × 400 kW dual-pump CDU + external dry coolers (one bay; rack positions stay IT) | same | same |

**Servers-per-rack is a chassis-height fact**: 42U holds 5 × 8U nodes or 6 × 6U — the 576-GPU
box commits you to a 6U chassis at server selection.

Scale reference: NVIDIA's GB300 NVL72 runs the same silicon at ~135–140 kW/rack `[fact]` — 9–10 such racks fill an LC-1,250, a configuration variant priced separately. Water-to-water CDU variant available for retrofit sites with an existing chilled-water plant.

## 4. The three-line estimate

```
1. IT load        = your GPU count ÷ 8 GPUs/server × per-server kW
2. Facility power = IT load × PUE          (air 1.40–1.50, FC 1.15–1.45, liquid 1.10–1.20)
3. Infra capex    = IT load (MW) × $3.6–4.9M/MW·IT   [canon, import duties included]
                    (before-duties band: $2.8–4.0M/MW·IT)
```

Annual energy, if you want line four: `IT × PUE × 8,760 h` — at $0.07/kWh that is ~**$0.61 M per MW of facility power per year** `[est., utility-rate dependent]` (so a 2.0 MVA draw ≈ $1.2 M/yr, as in the worked check below).

## 5. Estimate worksheets

### AC + H200 (2 servers/rack, 21 kW/rack — air box ~380-400 kW class)

| Your GPUs | Servers | Cabinets | IT load | Pod mapping | Infra capex `[est.]` | Utility feed `[est.]` |
|---:|---:|---:|---:|---|---:|---:|
| 64 | 8 | 4 | 84 kW | 1 × AC box, half-filled | $0.30–0.41 M | ~0.12 MVA |
| 288 | 36 | 18 | 378 kW | 1 × AC box (thermal fill limit) | $1.4–1.9 M | ~0.55 MVA |
| 576 | 72 | 36 | 756 kW | 2 × AC boxes | $2.7–3.7 M | ~1.1 MVA |
| 1,152 | 144 | 72 | 1,512 kW | 4 × AC boxes | $5.4–7.4 M | ~2.2 MVA |

### AC + B300 (2 servers/rack, 26 kW/rack — air box ~390 kW class)

| Your GPUs | Servers | Racks | IT load | Container mapping | Infra capex `[est.]` | Utility feed `[est.]` |
|---:|---:|---:|---:|---|---:|---:|
| 240 | 30 | 15 | 390 kW | 1 × AC box (thermal fill limit) | $1.4–1.9 M | ~0.57 MVA |
| 480 | 60 | 30 | 780 kW | 2 × AC boxes | $2.8–3.8 M | ~1.13 MVA |
| 960 | 120 | 60 | 1,560 kW | 4 × AC boxes | $5.6–7.6 M | ~2.26 MVA |

### LC + H200 (5 servers/rack 8U / 6 servers/rack 6U, 12 IT racks/container)

| Your GPUs | Servers | Racks | IT load | Container mapping | Infra capex `[est.]` | Utility feed `[est.]` |
|---:|---:|---:|---:|---|---:|---:|
| 480 | 60 | 12 | 630 kW | 1 × LC box (8U, 74%) | $2.3–3.1 M | ~0.73 MVA |
| 576 | 72 | 12 | 756 kW | 1 × LC box (6U variant, 89%) | $2.7–3.7 M | ~0.87 MVA |
| 1,152 | 144 | 24 | 1,512 kW | 2 × LC box | $5.4–7.4 M | ~1.74 MVA |
| 2,304 | 288 | 48 | 3,024 kW | 4 × LC box | $10.9–14.8 M | ~3.48 MVA |

### LC + B300 (4 servers/rack, 55 kW/rack, 14 IT racks/container)

| Your GPUs | Servers | Cabinets | IT load | Pod mapping | Infra capex `[est.]` | Utility feed `[est.]` |
|---:|---:|---:|---:|---|---:|---:|
| 256 | 32 | 8 | 432 kW | 1 × LC-850 (half-filled, upgrade path) | $1.6–2.1 M | ~0.50 MVA |
| 1,024 | 128 | 32 | 1,728 kW | LC-850 + LC-1,050 | $6.2–8.5 M | ~2.0 MVA |
| 2,048 | 256 | 64 | 3,456 kW | 5 × LC box (4.5 boxes; 5th half-filled) | $12.4–16.9 M | ~4.0 MVA |

### Container-per-GPU summary

| Container | + H200 | + B300 |
|---|---|---|
| **AC** (~400 kW thermal class) | 288 GPUs · ~380 kW | 240 GPUs · ~390 kW |
| **LC** (CDU bay, 12–14 racks) | 480 GPUs (8U) / **576** (6U) · 630–756 kW | 448 GPUs · 770 kW |

The density sleeper: cold-plating the 700 W H200 into a 6U chassis (6/rack) puts more GPUs in one 40-ft box than any other config. The per-GPU performance winner, at 2× the TDP, is LC + B300. And the air box's honest ceiling — ~380–400 kW, set by its in-box cooling plant, not its floor plan — is exactly why the market rarely sees a 500 kW air container.

Worked check on the 1,024-GPU B300 line: 1,024 ÷ 8 = 128 servers × 13.5 kW = 1,728 kW IT → × $3.6–4.9 M/MW = **$6.2–8.5 M**. Facility power 1,728 × 1.15 ≈ **2.0 MVA** feed. Annual energy ≈ 17.4 GWh → **~$1.2 M/yr** at $0.07/kWh `[est.]`.

## 6. What is NOT in these numbers

1. **GPU servers** — the largest line item in any AI build, priced separately and moving monthly.
2. **Land, pad, and medium-voltage upgrade** — the pod takes one LV feeder; if your site needs an MV to LV transformation stage, that's a separate civil package.
3. **Network fabric and storage** — inside the cabinets' customers' equipment, not ours.
4. **Opex beyond energy** — staffing, security, network transit.
5. **The import-duty line** — included in the $3.6–4.9 M band; if your supply chain changes, use the before-duties band and re-add duty at the prevailing rate.

## 7. Confidence and sources

- **`[fact]`** NVIDIA public specs: H200 SXM 700 W; B300 (Blackwell Ultra) 1,400 W; GB300 NVL72 rack ~135–140 kW, fully liquid-cooled.
- **`[canon]`** Site-held numbers: pod tiers and density bands ([turnkey pod spec](/solutions/turnkey-pod-spec/)); capex band incl. tariff ([pod page](/products/pod/) pricing ladder); 6–9 month delivery ([delivery playbook](/solutions/pod-delivery-playbook/)).
- **`[est.]`** Per-server input power, fluorine-pump PUE by climate, all worksheet multiplications, energy cost at an assumed $0.07/kWh. Pressure-test these first.
- Working papers with per-layer sizing and kill conditions: `docs/pod-research/02` in the project repo; the [three-chain anatomy](/technology/modular/) shows the topology the numbers assume.

## 8. Next step

Run your GPU count through §4, write down the two or three assumptions you'd dispute, and [bring them to us](/contact/) — the estimate call is free and the disputes are the point. Every quote ships with the same model we run our own capital through, kill conditions included.