Product FDC-P40 · the turnkey pod

Power in. Servers in.
Revenue out.

40-ft high-cube · 480 V direct-in · air 350–540 kW (AC-std) / liquid 850–1,250 kW · factory-built

6–9 mo
Signature to first power bill — permits run parallel to manufacturing
$2.8–4.0M
Turnkey, per MW·IT, air-cooled; liquid ×1.15
60–90 days
Factory build + FAT — all mature components, nothing waits on a roadmap
1–2 wks
On site to energized (air; 2–4 wks liquid with dry coolers)

01 What it is

The FDC-P40 (FlareDC Pod, 40-ft) is a 40-ft high-cube container with the whole chain factory-installed: low-voltage incomer, distribution busway, rack rows, cooling, monitoring. The customer's moves are exactly three — pour a pad, land one low-voltage feeder, plug in fiber — then rack servers and close the breaker. Power bill the same month, rent the same quarter.

BayFactory-installedLength
PowerLV incomer (ACB frame breaker + SPD + metering, UL 891), 400/480 V distribution busway, feeder columns, grounding~1.5 m
IT19″ rack rows with cold-aisle containment, dual-path PDUs / busway, fiber distribution~6.5 m
CoolingAir: smart DX / fluorine-pump FC, rooftop-skid mounted, N+1 · Liquid: CDU 2×(1+1) whole-unit backup, secondary loop, UQD quick-disconnects; dry coolers external~1.2–1.8 m
MonitoringSCADA/DCIM gateway (IEC 61850, Modbus, BACnet, SNMP), BMS, access/CCTV, leak detection, VESDA + clean-agent fire suppression~0.6 m
UPS (option)Modular double-conversion UPS + Li-ion (5–15 min); default omitted — AI training reruns, enterprise tenants opt in0–1.5 m

Outside the pod, the customer provides the pad (cured 28 days, poured in parallel with manufacturing), one low-voltage industrial feeder sized per the account below, dual fiber routes, and the servers themselves. Redundancy is honest: the default configuration is ≈ Tier I; dual feed, UPS, and 2N cooling are options that buy Tier II–III. Tell us the tier expectation before quoting — the expectation gap is where colo deals go to die.

02 Two versions, one power chain

Specifications are indicative and requirements-driven. Every value on this page — capacity tiers, rack counts, floor plans (the single-row 18-rack layout is a reference configuration, not a fixed design), cooling plant, footprint, delivery terms — is a starting point for engineering. The final configuration follows the customer's requirements and site conditions and is defined per order in the technical agreement, which prevails over this page.

FDC-P40-AC (air)FDC-P40-LC (liquid)
IT capacity tiers350 / 450 / 540 kW (AC-std). 500–750 kW belongs to the AC-WW wind-wall flagship — ◐ vendor-claim, opens after third-party verification850 / 1,050 / 1,250 kW
Rack density8–30 kW/rack main band (36 kW is the DX physical limit, peaks only)50–132 kW/rack — NVL72-class or cold-plate 4U nodes
RacksAC-std: single row, 18 IT + 2 network, cooling plant external (rooftop/skid). AC-WW ◐: 27 positions (25 IT + 2 network), back-to-back, no cold aisle10–14 racks, or 20 × 65 kW mixed
Cooling plantAC-std: ~480 kW installed DX/FC external, N+1 → ~400 kW usableCDU 2×N (1+1) whole-unit backup — survivor carries full IT ×1.1 (2×950 / 1,200 / 1,400 kW by tier), tie-bus + isolation valves, UPS-backed controls; external adiabatic dry-cooler bank, 3–4 large units (N+1) sized at 42 °C / 25 °C-wet-bulb ◐
PUE / WUE1.40–1.50 (Texas summer, est.)1.15–1.20 / <0.05 L/kWh, closed loop, no evaporation (est.)
Power input480 V / 60 Hz (US) or 380/400 V / 50 Hz, three-phase, straight in
Footprint12.19 × 2.44 × 2.90 m; liquid adds an external adiabatic bank: 3–4 units, ~80–120 m², ~63.5 dB(A) @ 10 m ◐ (setback or screening for night limits)

How to choose — the four-line account

  1. Server form factor picks the cooler. 2U/4U air-cooled nodes → air version. NVL72-class or cold-plate nodes → liquid. The cold plate is part of the server BOM; retrofitting later voids the warranty.
  2. Time beats PUE. A month of delay costs 30–100 months of PUE penalty, so the default play is air first, liquid second — the air version ships with the CDU position, pipework and leak tray pre-installed: swap servers, not the container.
  3. 3-year TCO: liquid wins by 15–25% with crossover at 18–24 months for high-utilization training; for 60–80% utilization hosting/inference, air's capex advantage holds.
  4. Texas summer is a design case, not a footnote. Above 40 °C ambient, dry-cooler output falls off a cliff [S2] — the liquid version ships with a summer strategy (adiabatic assist, higher supply temperature, or a derated SLA — your choice, in writing).

Zero water. The liquid version's closed PG25 loop with dry coolers runs at WUE <0.05 L/kWh — fully dry by default, no evaporation, no water rights, no drought negotiation. (The optional adiabatic summer assist trades a few hundred peak-hours of water a year for rated capacity in Texas heat.) In Texas counties where water is the permit fight, that is a siting argument, not a spec line.

03 The electrical first account

Feeder capacity ≥ IT capacity × design PUE ÷ 0.99, with 1.1–1.25× headroom (NEC continuous-load practice). Sizing at nameplate IT trips the first summer afternoon at full load — this one ×PUE is the most common quoting disaster in pod sales.

Frame-selection convention, disclosed: the frames in the table below are picked at the 1.1× floor on 100%-rated breakers. If your engineer applies the strict NEC 1.25× continuous rule to a thermally-rated (80%) frame instead, the top liquid tier sizes one frame larger (1,790 A × 1.25 = 2,238 A → 2,500 A frame). Which convention applies is fixed in the technical agreement, not discovered at commissioning.

Worked example: the 540 kW AC-std tier draws 783 kW of facility load at PUE 1.45 — about 950 A at 480 V (1,200 A at 380 V) — so the incomer is a 1,250 A frame. AC-WW 500–750 kW rows return with its verification.

VersionIT tierFacility load (×PUE)480 V380 VACB frame
Air (AC-std)350 kW508 kW (×1.45)620 A780 A800 A
450 kW653 kW790 A1,000 A1,000 A
540 kW783 kW950 A1,200 A1,250 A
Liquid850 kW1,003 kW (×1.18)1,220 A1,540 A1,600 A
1,050 kW1,239 kW1,510 A1,900 A2,000 A
1,250 kW1,475 kW1,790 A2,270 A2,000 A (2,500 A @380 V)

Only medium voltage on site? Two variants: a pad-mount transformer on the pad (34.5 kV / 480 V, ≈$60–90k US), or a transformer bay container mated to the pod (+$0.4–0.6M). Quote and schedule say which, before signature — not after.

04 From signature to power bill

StageDurationNote
Design freeze2–4 wksCooling version, tier, rack & PDU schedules, UPS yes/no
Permits & power application (parallel)3–6 moThe critical path — the factory never waits on it
Factory build + FAT60–90 days100% load for 24 h, 110% for 1 h, before it ever sees a truck
Ocean / road freight3–5 wks40-ft high-cube books as standard freight; pad cures in parallel
On site: land, connect, SAT1–2 wks air / 2–4 wks liquidGrounding ≤4 Ω, energization sequence, dummy-load 8 h
Rack + energize3–7 daysPDUs pre-wired to the customer's outlet schedule
Signature → power bill~6–9 monthsWhen permitting and manufacturing run in parallel

Every pod ships with a document pack: SLD and layout drawings, full FAT/SAT reports, SCADA point lists, O&M manuals with the derating curves, spares, and a 12-month warranty (compressors and CDU pumps 3–5 years, structure 10) starting at SAT sign-off.

05 The price ladder

All figures $/MW·IT, landed US — indicative; binding values are set per order in the technical agreement:

StepAirLiquid
Factory BOM, ex-works (est. — no public FOB quotes exist for AI pods; modeled from component pricing)$0.8–1.3M$0.8–1.2M
Turnkey quote, before import duties (design, certification, FAT, freight, margin)$2.8–4.0M$3.2–4.7M
Landed, import duties included$3.6–4.9M$4.0–5.7M
Optional UPS bay+$0.15–0.25M
Included, both liquids rows: CDU 1+1 whole-unit backup (+20–30% [est.] vs a pump-redundant-only plant — the colo-grade baseline, museReview §1.7)in the liquid bands above

External anchors: Duos' actual modular quote is $5.0M/MW (5 MW = $25M tenant capex, IEEE 2026); the JLL 2026 new-build global average is $11.3M/MW. The turnkey band lands at 25–50% of new-build — and the spread, not the discount, is the point: it is the margin pool for owning the infrastructure layer. Import duty is policy, not engineering — classification work happens before signature, and the before-duties band is the honest floor.

06 The honest economics

One 1.25 MW·IT liquid pod, three ways to hang it (rent shown in $/kW/month — a different unit from the $/MW·IT prices above, on purpose):

ArrangementArithmeticAnnual revenue
Base — wholesale colocation$195/kW/mo × 1,250 kW × 12$2.93M
Downside — contract-observed (≈$154/kW/mo)≈$1.85M/MW/yr × 1.25$2.31M
Upside — rent + GPU revenue kicker (5–10%)$2.31M + tenant upside share$3.9–5.4M

Against a $4.4–5.5M pod price that's a yield-on-cost of 20–40% depending on duty treatment — 2.4–4.6 years static payback. Full-caliber honesty: on the investment-decision basis ($6.56M/MW with duties included), static payback stretches to ~4.5–6.9 years [est., museReview §11.2] — and under the downside rent, 10-yr NPV @12% turns ≈ −$1.5M with payback ≈ 7.8 yr [est.]. That downside is exactly why we price rent first and walk from bull-case deals. Operating costs are counted, not waved: electricity ≈$0.77M/yr at $0.075/kWh and 80% utilization, plus ≈$0.35M/yr O&M, insurance and tax. Build-to-sell: a stabilized lease year later prices near $13.3M/MW (low confidence — no first-hand Texas comps; band $8–21M), which puts a two-year pod cycle in the 62–112% IRR range (tariff-friendly case; the conservative end matches high-cost builds).

Every figure in this section is a scenario calculation from our cost model, not a quote. The low-confidence ones are flagged inline — that's the house style. Engineering claims carry their published sources: the academic anchors ([S1] CDU failure timing — ASHRAE TC 9.9 secondhand + IEEE TCPMT 2021 · [S2] 42 °C derate — Applied Thermal Engineering 2022 · [S3] density ladder — IEEE TCPMT 2021 · [S4] grid queues — Nexus 2026).

07 Who else sells pods

PlayerProductScaleStatus, Oct 2026
Duos Edge AIEdge compute pod55 ft, 576 GPUs55 MW lease at $1.82M/MW/yr; sold its GPU business, back to landlording
LG CNSAI Box576 GPU + 1.2 MW/unitPlanned, zero deployments
HPEAI Mod POD≤1.5 MW/module$1.2B Vultr order
VertivMegaMod HDX144 racks / 10 MWBought UtilityInnovation for $2.6B, moving upstream into power
SchneiderEcoStruxure PodNVIDIA MGX-compatible$3B/5-yr Compass deal, ~150 units delivered
NVIDIADSX PODFactory-integrated container AI factory — 7× Vera Rubin NVL72, liquid, 800 VDC sitePartner ecosystem (Dell, HPE, Schneider, Vertiv, Crusoe…) delivers early 2027
CrusoeSparkTruck-delivered, 3 months200 MW+ running at Abilene; DSX POD ecosystem member
FDC-P4040-ft, 480 V direct-in, air + liquid, emptyOpen for 2027 slots

The read: Duos and LG sell pods with GPUs in them; Vertiv and Schneider sell million-dollar modules to general contractors. We sell the empty pod, low-voltage direct-in — no GPU balance sheet, no medium-voltage civil works, and the customer's own servers decide the refresh cycle. It is the smallest executable unit of the "own the infrastructure layer" thesis. NVIDIA just made the pod a product category — liquid-only, 800 VDC-only, GPUs included. Our lane is what it can't serve: the 480 V installed base that picks its own silicon.

Where the format stops winning, stated plainly: modular's advantage is consistent below ~20 MW; by 50–100 MW traditional construction closes the gap — Inflect drew that line themselves, and Duos sells modular pods while spending $30M on a conventional campus. Under 20 MW we're the right tool; above it, we'll tell you before you ask.

08 Quote in three questions

  1. What servers? 2U/4U air-cooled → AC version. NVL72-class or cold-plate → LC version.
  2. What power do you hold? 380/480 V service → direct-in. Only medium voltage → transformer variant, priced and scheduled up front.
  3. What tier? Default ≈ Tier I. Dual feed, UPS, 2N cooling → Tier II–III, itemized.

Send the three answers to [email protected] and the quote comes back with the tariff treatment and the permit calendar already in it. Deployed pods go to [email protected] — monitored 7×24.

Request a pod quote Compare the three delivery paths Read the product brief

Specs are the planning baseline (spec book v3.2); figures marked est. are assumptions, not vendor commitments. Electrical parameters are finalized in the customer–vendor technical agreement per NEC / local code.