Solutions Delivery paths

Three ways to land
a megawatt

Retrofit · Pod deployment · Site conversion — one model, honest verdicts

We don't sell one answer to every site. We run your project through the same model we run our own capital through — 11% discount rate, ten-year hold, unified rent and tariff assumptions — and the verdict follows the only variable that matters: who already holds the power. Three engagements cover the field. Each one below states who it is for, what we deliver, what it costs, and the kill condition — because a solution without a kill condition is a pitch.

Path Retrofit — energize white space you already hold

For: owners of legacy data centers or industrial buildings with committed power — the 5 MW Dallas profile.

What we deliver: power due diligence first, retrofit in place second. No new substation, no interconnection queue — the median grid wait is over five years, and inherited energized floor space is pricing power in a DFW market running 1.8–2.8% vacancy.

$4.25M
All-in per MW ($21.3M for the 5 MW case)
6–10 mo
Deployment (45-day light-retrofit precedent exists)
21.9%
Base IRR — PROCEED; bear-case rent still clears 7.0%
1
Kill condition: the "spare" power must survive due diligence

The verdict voids outright if diligence shows the spare megawatts aren't actually deliverable — which is why the diligence is the first deliverable, not the last. The full working paper: Three Ways to Land a Megawatt in Texas.

Path Pod deployment — buy the time premium

For: sites with land and a low-voltage feeder (or medium voltage we bridge) that need capacity in months, not queue-years.

What we deliver: turnkey FDC-P40 pods — a 40-ft container with LV power, distribution, racks, cooling and monitoring factory-installed. You pour the pad, land one feeder, plug in fiber. Manufacturing (60–90 days) runs parallel to permitting, which is the critical path.

6–9 mo
Signature to first power bill
$3.6–4.9M
Per MW·IT landed, duties included; before duties $2.8–4.0M
20–40%
Yield-on-cost held for rent
24.3%
5-yr exit IRR at $13.3M/MW — the S2 trade (anchor low-confidence, no Texas comps)

Held ten years this path is mediocre (10.0% IRR) — that was never the business. Six-month go-live against a five-year queue means cash starts ~54 months early: sell the time premium, not the rent. The wildcard is import duty

Path Site conversion — mines and powered industrial sites

For: owners of already-powered sites — mines, factories — where the real asset is the substation, the interconnection rights, and the capacity.

What we deliver: a scope-frozen conversion. Same 20 MW site produces three different verdicts depending only on scope, so we price the boundaries before you spend:

$1.5–3.6M
Light retrofit per MW, air-cooled H100/H200, ~45 days → PROCEED
$5.80M
Base conversion per MW → CONDITIONAL (26.8% exit IRR)
$10.25M+
Full AI-ready delivery per MW → NO-GO at our model rates
≈$1.25M
Scrap-value context of the mining hardware per MW — the site is what you're buying

Scope discipline is the investment thesis here: light retrofit proceeds, the base case negotiates an exit, and full AI-ready delivery never clears our hurdle — we will tell you that before the engagement, not after.

04 The line we hold on every engagement

All three paths are modeled at $190–195/kW/month — deliberately below the Dallas outlook floor of $200. Push rents to the bull case ($240–260) and every IRR lands at 21.5–31.7%. Drop to bear ($140–150) and every NPV goes negative. A dollar won at the signing table beats a decade of PUE engineering: we price the rent first and compress losses second — and we won't take an engagement priced on the bull case.

Bring us your site Back to scenarios

Figures are scenario calculations (Oct 2026 model), not offers; every engagement re-runs the model on your site's tariffs, rents and power reality. The working documents behind every number on this page are in the technical references library.