Solutions Delivery paths
Three ways to land
a megawatt
We don't sell one answer to every site. We run your project through the same model we run our own capital through — 11% discount rate, ten-year hold, unified rent and tariff assumptions — and the verdict follows the only variable that matters: who already holds the power. Three engagements cover the field. Each one below states who it is for, what we deliver, what it costs, and the kill condition — because a solution without a kill condition is a pitch.
Path Retrofit — energize white space you already hold
For: owners of legacy data centers or industrial buildings with committed power — the 5 MW Dallas profile.
What we deliver: power due diligence first, retrofit in place second. No new substation, no interconnection queue — the median grid wait is over five years, and inherited energized floor space is pricing power in a DFW market running 1.8–2.8% vacancy.
The verdict voids outright if diligence shows the spare megawatts aren't actually deliverable — which is why the diligence is the first deliverable, not the last. The full working paper: Three Ways to Land a Megawatt in Texas.
Path Pod deployment — buy the time premium
For: sites with land and a low-voltage feeder (or medium voltage we bridge) that need capacity in months, not queue-years.
What we deliver: turnkey FDC-P40 pods — a 40-ft container with LV power, distribution, racks, cooling and monitoring factory-installed. You pour the pad, land one feeder, plug in fiber. Manufacturing (60–90 days) runs parallel to permitting, which is the critical path.
Held ten years this path is mediocre (10.0% IRR) — that was never the business. Six-month go-live against a five-year queue means cash starts ~54 months early: sell the time premium, not the rent. The wildcard is import duty
Path Site conversion — mines and powered industrial sites
For: owners of already-powered sites — mines, factories — where the real asset is the substation, the interconnection rights, and the capacity.
What we deliver: a scope-frozen conversion. Same 20 MW site produces three different verdicts depending only on scope, so we price the boundaries before you spend:
Scope discipline is the investment thesis here: light retrofit proceeds, the base case negotiates an exit, and full AI-ready delivery never clears our hurdle — we will tell you that before the engagement, not after.
04 The line we hold on every engagement
All three paths are modeled at $190–195/kW/month — deliberately below the Dallas outlook floor of $200. Push rents to the bull case ($240–260) and every IRR lands at 21.5–31.7%. Drop to bear ($140–150) and every NPV goes negative. A dollar won at the signing table beats a decade of PUE engineering: we price the rent first and compress losses second — and we won't take an engagement priced on the bull case.