Solution brief
Three Ways to Land a Megawatt in Texas: Retrofit, Factory, or Mine
Scenario planning, on the record. None of these three projects exists — no site was bought, no pod delivered, no dollar spent. They are modeled verdicts (11% discount rate, 10-year hold) showing how we evaluate engagements before committing. Asked to ‘see the place’: there is no place yet — that is exactly what the numbers below are for.
Run three Texas paths through the same model — 11% discount rate, 10-year hold, unified rent and import-duty assumptions — and the verdicts split. Not because the parameters were tilted, but because the paths themselves differ in the only thing that matters: who already holds the power.
The scoreboard
| S1: Legacy IDC retrofit (Dallas, 5 MW) | S2: Factory + containers (10 MW) | S3: Miner conversion (20 MW) | |
|---|---|---|---|
| Capex / MW | $4.25M | $6.56M | $5.80M (base) |
| Base NPV / IRR | +$13.58M / 21.9% | −$3.24M / 10.0% | −$2.99M / 10.5% |
| Payback | 4.5 yr | 6.6 yr | 6.5 yr |
| 5-yr exit IRR @ $13.3M/MW* | 43.4% | 24.3% | 26.8% |
* Exit-anchor disclosure: $13.3M/MW is a low-confidence figure — no first-hand Texas comps; the stabilized-asset band runs $8–21M. Every exit-numbered IRR in this brief inherits that uncertainty. | Verdict | PROCEED | CONDITIONAL | CONDITIONAL |
S1: the cheapest MW is the already-energized MW
The Dallas retrofit wins for one reason: it inherits 5 MW of committed power. No new substation, no interconnection queue (median wait: over five years). In a DFW market running 1.8–2.8% vacancy, energized floor space is pricing power. Even the bear case — rent at $140/kW/month — still clears a 7.0% IRR. Its one kill-condition: if due diligence shows the “spare” 5 MW isn’t actually deliverable, the verdict voids outright.
S2: sell the time premium, not the rent
Held for ten years, the factory-plus-container play is mediocre (10.0% IRR). That was never the business. Six-month go-live against a five-year queue means cash starts ~54 months early, and a year-5 exit at $13.3M/MW — the low-confidence anchor disclosed above — lifts IRR to 24.3%. S2 is a trade on schedule certainty — the delay tax made liquid — with import duties as the wildcard that can reprice the whole entry.
S3: the mine is a function of scope, not of location
Same 20 MW site, three verdicts. Light retrofit for air-cooled H100/H200 (~$1.5–3.6M/MW, 45 days) → PROCEED. Our base case ($5.8M/MW) → CONDITIONAL. Full AI-ready delivery ($10.25–11.5M/MW) → NO-GO. The asset being bought is the substation, the interconnection rights, and the capacity — mining hardware is worth roughly $1.25M/MW as scrap-value context. Scope discipline is the investment thesis.
Rent outranks everything
All three scenarios assume $190–195/kW/month — deliberately below the Dallas outlook floor of $200. Push rents to the bull case ($240–260) and every IRR lands at 21.5–31.7%. Drop to bear ($140–150) and every NPV goes negative. A dollar won at the signing table beats a decade of PUE engineering: price first, compress losses second.
The one-line version
Inherit power and you PROCEED; manufacture time and you negotiate an exit; buy a mine and freeze the scope before it melts. The megawatt was never the hard part — the energized megawatt is. The container that delivers it is spec’d here; what it costs, here.